Share

The Gorgon LNG Project is now 90 percent complete. All the subsea pipelines, wellheads and associated facilities for Gorgon and Jansz-lo fields are completed. All 18 subsea wells have been drilled and are complete. Pre-commissioning activities are under way on the subsea facilities at both fields.

Delivery of modules required for LNG Train 2 continues. All Train 1 modules and 13 of 17 Train 2 modules are on their foundations. Both LNG Tanks are now ready for LNG. Construction is complete on three of the four condensate tanks.

The jetty is complete except for the loading arm installation. The domestic gas pipeline is now connected from the mainland through the jetty to the plant site and pre-commissioning activities are complete.

With permanent power to the permanent operations facility, the first members of the operations team have started commissioning and monitoring systems in the central control room. Construction and pre-commissioning activities are complete for one of the four ground flare boxes.

The Gorgon Project is developing the Gorgon and Jansz-Io gas fields, located within the Greater Gorgon area, between 130 and 220 kilometres off the northwest coast of Western Australia.

It includes the construction of a 15.6 million tonne per annum (MTPA) liquefied natural gas (LNG) plant on Barrow Island and a domestic gas plant with the capacity to supply 300 terajoules of gas per day to Western Australia.

Gorgon LNG will be off loaded via a 2.1 kilometre long loading jetty for transport to international markets. The domestic gas will be piped to the Western Australian mainland.

The project also includes the design, construction and operation of facilities to inject and store CO2 into a deep reservoir unit – known as the Dupuy Formation – more than two kilometres beneath Barrow Island.

This will reduce greenhouse gas emissions from the project by approximately 40 per cent. The Australian government has committed $60 million to the Gorgon Carbon Dioxide Injection Project as part of the Low Emissions Technology Demonstration Fund.

 

Related articles
0 Comments

©2024 Pump Industry. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

or    

Forgot your details?

Create Account