The new fluoride dosing facility servicing Brisbane’s major water treatment plants at Mt Crosby undergo commissioning from late July 2018 and is expected to be fully operational in August 2018.

Commissioning of the refurbished Holts Hill fluoride dosing facility was delayed to allow upgrade works to the East Bank Water Treatment Plant to be completed.

Commissioning of the new Holts Hill fluoride facility requires both Mt Crosby plants to be operational. The East Bank works were in preparation for a major filter upgrade to the plant planned for 2019. Both Mt Crosby plants are critical, supplying up to 50 per cent of South East Queensland’s daily drinking water supply.

This is the first major upgrade of a fluoride dosing facility since fluoridation was introduced into South East Queensland in 2009.

Find Chemicals And Plastics Related Companies In The Pump Industry Capability Guide



Related articles
0 Comments

©2024 Pump Industry. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

or    

Forgot your details?

Create Account