Queensland Urban Utilities is upgrading 12 sewerage pump station switchboards across Brisbane to extend their operational life and improve the reliability of the network.
Construction will include excavation of the existing site and installation of a concrete foundation and a new switchboard.
The following table identifies the Sewerage Pump Station Switchboards to be upgraded and key construction timings, weather permitting.
# | Location | Construction commencement | Construction completion | Duration |
1 | Pritchard Street, Lytton | 27 March 2013 | 8 April 2013 | 2 weeks |
2 | Anton Street, Hemmant | 8 April 2013 | 15 April 2013 | 1 week |
3 | Hall Street, Brighton | 12 April 2013 | 22 April 2013 | 1 week |
4 | Balcara Avenue, Carseldine | 15 April 2013 | 1 May 2013 | 2.5 weeks |
5 | Halleys Crescent, Bridgeman Downs | 22 April 2013 | 16 May 2013 | 3.5 weeks |
6 | Links Avenue South, Eagle Farm | 30 April 2013 | 7 May 2013 | 1 week |
7 | Lobe Street, Bald Hills | 7 May 2013 | 22 May 2013 | 2 weeks |
8 | Evergreen Street, Bracken Ridge | 16 May 2013 | 3 June 2013 | 2.5 weeks |
9 | Gympie Road, Bald Hills | 22 May 2013 | 29 May 2013 | 1 week |
10 | Millers Road, Underwood | 5 June 2013 | 13 June 2013 | 1 week |
11 | Ormuz Street, Yeronga | 13 June 2013 | 20 June 2013 | 1 week |
12 | Kimberley Street, Oxley | 17 June 2013 | 24 June 2013 | 1 week |