SA Water’s $18 million upgrade of the Port Lincoln Wastewater Treatment Plant has reached a major milestone, with the new anaerobic digester’s 20 tonne steel cover craned into place.

Resembling a ‘flying saucer’ while it was shifted through the air, the cover caps off the majority of the digester’s construction, which includes the structure’s round walls and installation of internal pipework.

SA Water Senior Manager Production and Treatment, Lisa Hannant, said safety was at the forefront of the cover lift and the team undertook significant planning in preparation.

“It’s an incredible feat and people might not be aware of the work behind the scenes to ensure a safe, successful operation,” Ms Hannant said.

“The digester has been engineered to support the weight of the cover and we carried out a range of investigations to enable the lift, including compaction testing of the ground the crane sat on and an extensive bearing capacity assessment.

“The lid is actually a floating cover and sits comfortably in voids, controlled by guide rails and rollers – moving up and down depending on capacity within the digester, which is also sealed by water to prevent the escape of biogas generated during the digestion process.

“Our biogas is then extracted and burnt to provide a source of heat for the digester, helping to hold waste at a constant 38 degrees to create an optimal environment for the bacteria inside.”

Anaerobic digesters are large, sealed concrete tanks that heat the solid organic waste from sewage – known as sludge – in an oxygen-free environment, to promote the natural bacterial metabolic processes that break it down.

The new infrastructure will reduce methane emissions, and improve odour management and the long-term operability of the treatment plant.

Ms Hannant said local Port Lincoln contractors were playing a key role in the plant’s upgrade.

“With a state-wide network and continuous focus on sustaining our infrastructure, there’s often opportunities to work together and support local businesses and communities,” Ms Hannant said.

“Keeping it local, where possible, can lead to a positive economic and social impact for the community we’re working within, while enabling us to tap into their expertise and knowledge for the benefit of our wider project.

“There’s around 40 full-time employees working at the plant on any given day to deliver this project and they’ve already built two pump station chambers, concrete footings and structural steelwork for new site buildings, and are now progressing our digested waste hardstand and standby storage lagoon.

As part of the wider program, SA Water invested $6 million to increase the capacity of the sewerage pipe network, which included the upgrade of a wastewater pumping station and four kilometres of new sewer main around the Port Lincoln Marina.

The upgrade of SA Water’s Port Lincoln Wastewater Treatment Plant marks the final stage of the program, and is expected to be complete by December 2020.

Find Sewage Pumping Stations Related Companies In The Pump Industry Capability Guide



Related articles
0 Comments

©2024 Pump Industry. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

or    

Forgot your details?

Create Account