The construction of the new Goolwa Surf Life Saving Club (SLSC) facility has reached a key milestone, with excavation works commencing to allow for  the installation of a 20,000L wastewater holding tank, grease arrestor and new council wastewater pump station chamber.

Initial construction work commenced at the beginning of August 2018 and has progressed quickly. Substantial excavation works commenced adjacent to the facility on 4 December 2018, to allow for the installation of key infrastructure components to service the building.

Performing these works simultaneously will increase project efficiencies and reduce overall inconvenience for the community and visitors alike.

These excavation works are expected to be completed by late December 2018, before Christmas.

Find Related Companies In The Pump Industry Capability Guide



Related articles
0 Comments

©2024 Pump Industry. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

or    

Forgot your details?

Create Account