Share

A milestone has been reached for SA Water’s Bolivar WasteWater Treatment Plant upgrade with more than 310 cubic metres of concrete poured to create the inlet’s foundation.

The concrete pour involved the coordination of around 50 mixing trucks across the complex 15-hour task.

Bolivar’s new inlet will significantly increase the plant’s capacity to receive and process sewage in preparation for higher projected flow rates, as Adelaide’s population grows into the future.

SA Water’s Senior Manager of Capital Delivery, Peter Seltsikas, said that along with the slab pour, the project has achieved a number of other milestones in delivering one of the plant’s largest upgrades.

“Through early procurement, we’ve now taken delivery of new screens which will be retrofitted on the inlet and act as the plant’s first line of defence to capture and remove inorganic material.

“We’ve also recently started replacing three of our existing inlet pipes – which transfer raw sewage from across metropolitan Adelaide to the plant – while they remain temporarily connected to the existing inlet structure.

“Once the new inlet is complete, we’ll change the connections over and construct an additional three inlet pipes, to accommodate increased flows that will come into the plant as the local population grows.”

Mr Seltsikas said that despite ticking off the project’s single largest concrete pour, SA Water anticipates a further 1,990 cubic metres will be required, with the team now working on forming the concrete roof structure, overflow channels and walls.

“At this stage, we’re hoping to begin installing the inlet’s mechanical equipment in the next few months, which involves our eight customised screens, major support steel structure, and ancillary items such as penstocks and stop logs that control and isolate the flow of sewage.”

Among the project’s other recent milestones was the use of a 20-tonne tower crane next to the inlet’s concrete slab to help crews lift equipment and pipes into place, along with large panels to facilitate concrete form work.

To keep in step with future projected flows, Bolivar’s capacity to receive sewage from the network will more than double to around 630 million litres per day once the new inlet is operational.

Featured image: The first concrete poured at the Bolivar WasteWater Treatment Plant upgrade. Image credit: SA Water.

Find Sewage Pumping Stations Related Companies In The Pump Industry Capability Guide



Related articles
0 Comments

©2024 Pump Industry. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

or    

Forgot your details?

Create Account